Work Order
COMPLETED
Equipped Painting
License# EQUIPSL817K2
401 Olympia Ave NE Box #33, Renton, Washington 98056
(425) 370-7267
Proposal #
1448420
Date
3/15/2025
Crew Notes
Special Notes/Client Requests:
Color Schedule: TBD
SOFT SCHEDULE/DEADLINES:
- Start and finish 3/28
PAINT/Gallons:
- 2-3 Gallons
SUPPLIES/MATERIALS:
- Basic Interior
TOOLS/EQUIPMENT:
- 6' Ladder
LABOR:
- CREW SIZE - 1
- LABOR HOURS - 6 -8 hours
- SUB BUDGET - $325 all labor paint and materials
Item
Quantity
Interior Painting - Walls
1.00
Includes Labor, Paint, and Materials
Preparation:
- Move furniture away from application areas
- Cover and protect all floors and furniture with drop cloths and plastic sheets where necessary
- Remove all outlet covers & re-install
- All cracks and nail holes will be caulked and filled where necessary
- (2) Coats Brush and Roll Application (all walls one color)
Paint:
SHERWIN-WILLIAMS
- Quality - Promar 200 0 VOC
- Color - TBD
- Sheen - Egshell
Areas of Application:
- Office Walls
Does NOT Include:
-
Closets, Trim, and Ceiling
Office Ceiling
Change Order: 03/25/2025
1.00
Includes Labor, Paint, and Materials
Preparation:
- Cover and protect all floors and furniture with drop cloths and plastic sheets where necessary
- Mask fans & light fixtures where necessary
- (2) Coats Brush and Roll Application
- color to be the same color as walls
Brand:
- Sherwin-Williams
Product:
- Promar 200 0 Voc
Sheen:
- Egshell
Application Areas:
- Office Ceiling
Does Not Include:
- Closet
Duration Paint Upgrade
Change Order: 03/29/2025
3.00