Crew Notes

JOB PLAN:(3½- 6 DAYS)

  • Arrive on sceduled time and unload supplies
  • Wait for Project Manager to go over Plan
  • Go in and set up masking, drop-cloths, and other tools you may need (details below of what you might need)(should take about 1-2hours)
  • TEST PRODUCTS FROM SW: Touch-up to see if match (10-30mins, while setting up masking)
  • If paint matches, tell PM so they can order the paint. If painy does not match, re-correct color at SW store and repeat process.
  • Start downstairs and repair nail noles, gashes in trim and drywall (5mins-1hour)
  • Let repair mud/wood putty dry (30mins-1hour)
  • Paint walls and ceilings(1-2 coats refresh)(1-3days),  EXCLUDE INVERTED/RECESSED CEILING in left room of entryway
  • Touch-Up wainscoting and trim(2-6hours)
  • Paint EXTERIOR of front double doors(4-6 hours), preferably do this while interior walls/ceiling is being painted
  • Repeat procedure upstairs, Repair to Paint to Touch-up trim/wainscoting (1-2days)
  • Stairwell can be addressed before or after upstairs procedures. ONLY doing the spindels on handrails. Walls and ceiling full repaint. Wainscoting needs repair and touch-up (4-8hours)
  • *Particular doors, frames and trim may need wood putty and repair* (2-6 hours)
  • Clean-up and remove masking, load up vehicle with all waste and supplies (should take about 1- 2hours)
  • If client is present show them the work completed, ask if they have questions, comments, or concerns and THANK THEM for the opportunity to work with them and ask them to look for the Google Review emailed to them after invoicing (should take a few moments 5-10 mins)
  • LOG 'DAILY LOGS' and leave property

MATERIALS/ PAINT/ SUPPLY CHECKLIST:

  • Sheetrock joint compound (mud), lightweight or fast drying (5, 20, 40, minute mud)
  • masking tape
  • sheet plastic
  • drop-cloths
  • paint brush
  • 9" rollers, 4" mini-rollers, and frames for rollers
  • contractor trash bags
  • rags for cleanup
  • Orangepeel texture can(s)
  • 1 gal of primer where needed preferably Quick Dry (green label from Sherwin-Williams)
  • 25-30 gals of MATCHED paint COLOR & SHEEN ( TBD, pickup at disclosed Paint Store w/primer)
  • ANYTHING ELSE NOT MENTIONED ABOVE THAT WOULD BE USEFUL ON THIS PROJECT
Item
Quantity
Interior Painting - Walls and Ceiling Only
3420.00

Includes Labor, Paint, and Materials 

Preparation:

  • Cover and protect all floors and furniture with drop cloths and plastic sheets where necessary
  • Caulk/Patch Stress Cracks and Nail Pops as Needed
  • Remove & re-install window treatments where necessary (blinds, drapery)
  • Remove all outlet covers & re-install 
  • All cracks and nail holes will be caulked and filled where necessary
  • (1-2) Coats Brush and Roll Application

    Paint Brand: 

    • Sherwin-Williams

    Grade: 

    Color/Sheen: 

    • Color and Sheen to Match Existing

    Areas of Application: 

    • Main Level Home - Entrance Walls, Den Closet walls and ceilings, Downstairs Bathroom Walls and Ceilings, 2 Downstairs Hallway Walls, Downstairs Closet Walls, Dining Room Walls,  Laundry Walls, Kitchen Walls, and Living Room Walls 
    • Stairwell Walls 
    • 2nd Floor: Hallway Walls, Master Bedroom Walls and Ceilings, Master Bathroom/Closet Walls and Ceilings, New York Room Walls and Ceilings, Bonus Room Walls and Ceilings, and Left Corner Bedroom/Closet Walls and Ceilings 

Interior Painting - Trim (Touch Ups and Some Full Paint)
1.00

*Goal for the trim is take care of major trim damaged areas and scuffs.  Majority touch ups to be conducted unless stated below.  *Trim Paint color May have slight difference in sheen/color

Preparation: 

  • Wipe trimwork to remove dust & debris 
  • All cracks and nail holes will be caulked and filled where necessary
  • To ensure proper paint adhesion, all glossy surfaces and trim will be sanded and cleaned (as needed). Any rough areas will be sanded to remove flaking paint. 
  • (1-2) Coats Brush and Roll Application

    Includes:

    • Touch Up Areas Include: Wainscoting, baseboards, doors, window frames, and door frames
    • Full Paint: Upstairs Bonus Room Door, Downstairs Dining Room Window Sill, Main Post Spindles, Interior Side of Entry Double Door, 3-4 Door Frames, and Stairwell Landing Wainscoting

    Areas of Application: 

    • Sherwin-Williams

    Product:

    • Emerald Urethane Trim Enamel or Proclassic 

    Color/Sheen:

  • Color and Sheen to Match Existing


Front Doors - Double Doors
1.00

Exterior Painting - Includes Labor, Paint, Equipment & Supplies


Surfaces Include:
2 double front doors to be painted in black 


Does not Include:
- Door Frames 


Exterior Scope of Work:
- Proper Surfaces Preparation on all unpainted area; Protection of hardware 

- Masking and prepping of all windows prior to paint application
- (2) Coats Spray Finish 


Paint:

Sherwin Williams Premium Exterior Paint - Emerald Trim Urethane 

Color/Sheen:

Tricorn Black Satin 

*Any unforeseen damages or repairs will be an additional charge unless otherwise stated.


Upstairs Right Corner Bedroom Walls and Ceiling
1.00

Includes Labor, Paint, and Materials 

Preparation:

  • Cover and protect all floors and furniture with drop cloths and plastic sheets where necessary
  • Remove & re-install window treatments where necessary (blinds, drapery)
  • Remove all outlet covers & re-install 
  • All cracks and nail holes will be caulked and filled where necessary
  • To ensure proper paint adhesion, all glossy surfaces and trim will be sanded and cleaned (as needed). Any rough areas will be sanded to remove flaking paint
  • (1-2) Coats Brush and Roll Application

    Paint Brand: 

    • Sherwin-Williams

    Grade: 

    Color/Sheen: 

    • To Match existing color/sheen

    Areas of Application: 

    • Walls and Ceiling in Upstairs Right Corner Bedroom (left of Bonus Room)